32.6.1.1 Dismantling of R.C.C. beam, lintel, column, drop wall, sun shade from any height and removal of debris to a safe distance.

Considering 1 cum of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 2.5 nos 600 per day 600 1500
2 Ordinary labour Ordinary labour 2 no 550 per day 550 1100
3 Scaffolding Scaffolding 2.5 sqm 10 per sft 107.6 269
4 Ordinary labour Brooming, cleaning etc. 1 LS 550 per day 82.5 82.5
5 Ordinary labour T & P, sundries etc. 1 LS 550 per day 550 550
Sub-Total 3501.5
Contractor's Profit 10% 0.1 350.15
Contractor's Overhead Expenses 3.5% 0.035 122.55
Total 3974.2
Add VAT with adjustment factor. 1.08108 7.5% 0.075 322.23
Grand Total 4296.43
Rate per cum 4296
Rate per cum 4296