Considering 10 sqm of works
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour Skilled labour | 1 | nos | 600 | per day | 600 | 600 | |
| 2 | Ordinary labour Ordinary labour | 1.5 | no | 550 | per day | 550 | 825 | |
| 3 | Scaffolding Scaffolding | 2.5 | sqm | 10 | per sft | 107.6 | 269 | |
| 4 | Ordinary labour Brooming, cleaning etc. | 1 | LS | 550 | per day | 82.5 | 82.5 | |
| 5 | Ordinary labour T & P, sundries etc. | 1 | LS | 550 | per day | 110 | 110 | |
| Sub-Total | 1886.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 188.65 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 66.03 | |||||
| Total | 2141.18 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 173.61 | ||||
| Grand Total | 2314.79 | |||||||
| Rate per sqm | 231.5 | |||||||
| Rate per cum | 2315 | |||||||