Considering 1 cum of works
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour Skilled labour | 2 | nos | 600 | per day | 600 | 1200 | |
| 2 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| 3 | Scaffolding including safety provision Scaffolding/safety prop etc. | 2.5 | sqm | 12 | per sft | 129.12 | 322.8 | |
| 4 | Ordinary labour Brooming, cleaning etc. | 1 | LS | 550 | per day | 82.5 | 82.5 | |
| 5 | Ordinary labour T & P, sundries etc. | 1 | LS | 550 | per day | 550 | 550 | |
| Sub-Total | 2705.3 | |||||||
| Contractor's Profit | 10% | 0.1 | 270.53 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 94.69 | |||||
| Total | 3070.52 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 248.96 | ||||
| Grand Total | 3319.48 | |||||||
| Rate per cum | 3319 | |||||||
| Rate per cum | 3319 | |||||||