Breakup

32.6.2 Dismantling of R.C.C. in roof slab and removal of debris to a safe distance.

Considering 1 cum of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 2 nos 600 per day 600 1200
2 Ordinary labour Ordinary labour 1 no 550 per day 550 550
3 Scaffolding including safety provision Scaffolding/safety prop etc. 2.5 sqm 12 per sft 129.12 322.8
4 Ordinary labour Brooming, cleaning etc. 1 LS 550 per day 82.5 82.5
5 Ordinary labour T & P, sundries etc. 1 LS 550 per day 550 550
Sub-Total 2705.3
Contractor's Profit 10% 0.1 270.53
Contractor's Overhead Expenses 3.5% 0.035 94.69
Total 3070.52
Add VAT with adjustment factor. 1.08108 7.5% 0.075 248.96
Grand Total 3319.48
Rate per cum 3319
Rate per cum 3319
Help