32.6.3 Recovery of reinforcing bars and metals during dismantling of RCC including cleaning, making bundle, stacking or storing as per direction of engineer in charge and removal of debris to a safe distance.

Considering 50 kg

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.1 no 600 per day 600 60
2 Ordinary labour Ordinary labour 0.25 no 550 per day 550 137.5
3 Ordinary labour Cleaning rust and foreign materials 1 LS 550 per day 27.5 27.5
4 Ordinary labour T & P, sundries etc. 1 LS 550 per day 27.5 27.5
Sub-Total 252.5
Contractor's Profit 10% 0.1 25.25
Contractor's Overhead Expenses 3.5% 0.035 8.84
Total 286.59
Add VAT with adjustment factor. 1.08108 7.5% 0.075 23.24
Grand Total 309.83
Rate per kg 6.2
Rate per quintal 12.4