Considering 1 cum
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| 2 | Ordinary labour T & P, sundries etc. | 1 | LS | 550 | per day | 11 | 11 | |
| Sub-Total | 286 | |||||||
| Contractor's Profit | 10% | 0.1 | 28.6 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 10.01 | |||||
| Total | 324.61 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 26.32 | ||||
| Grand Total | 350.93 | |||||||
| Rate per cum | 351 | |||||||
| Rate per cum | 351 | |||||||