Breakup

32.6.6 Recovery of brick bats during dismantling of soling, brick works, HBB etc. including cleaning, stacking or storing as per direction of engineer in charge and removal of debris to a safe distance.

Considering 1 cum

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
2 Ordinary labour T & P, sundries etc. 1 LS 550 per day 11 11
Sub-Total 286
Contractor's Profit 10% 0.1 28.6
Contractor's Overhead Expenses 3.5% 0.035 10.01
Total 324.61
Add VAT with adjustment factor. 1.08108 7.5% 0.075 26.32
Grand Total 350.93
Rate per cum 351
Rate per cum 351
Help