Breakup

32.7 Repairs to minor/fine (non-structural affecting aesthetic) cracks in brick walls, floor and roof etc.

Considering 30 meter of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.3 no 600 per day 600 180
2 Mason / Mosaic mistry Mason 0.5 no 700 per day 700 350
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to mason 0.5 no 550 per day 550 275
4 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement (or any approved bonding agent 0.1 bags 410 per bag 410 41
5 Sand (F.M. 1.2) Sand (F.M. 1.2) 0.014 cum 1900 per % cft 670.89 9.39
6 Ordinary labour T & P, scaffolding, ladder sundries etc. 1 LS 550 per day 165 165
Sub-Total 1020.39
Contractor's Profit 10% 0.1 102.04
Contractor's Overhead Expenses 3.5% 0.035 35.71
Total 1158.14
Add VAT with adjustment factor. 1.08108 7.5% 0.075 93.9
Grand Total 1252.04
Rate per meter 41.73
Rate per meter 41.73