Breakup

32.8.1 Cutting and polishing of old mosaic on wall with pumice stone etc.

Considering 10 sqm of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
2 Skilled labour Skilled labour 1 no 600 per day 600 600
3 Pumice stone for finishing mosaic work pumice stone 0.2 no 175 each 175 35
4 Oxalic acid Oxalic acid 0.05 liter 105 per litre 105 5.25
5 Wax for polishing Wax polish 0.125 kg 300 per kg 300 37.5
6 Ordinary labour Brooming, cleaning etc. 1 LS 550 per day 55 55
7 Ordinary labour T & P, sundries etc. 1 LS 550 per day 55 55
Sub-Total 962.75
Contractor's Profit 10% 0.1 96.28
Contractor's Overhead Expenses 3.5% 0.035 33.7
Total 1092.73
Add VAT with adjustment factor. 1.08108 7.5% 0.075 88.6
Grand Total 1181.33
Rate per sqm 118.1
Rate per sqm 118.1