Breakup

32.8.3 Cleaning and washing the mosaic floor etc.

Considering 10 sqm of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.2 no 600 per day 600 120
2 Bleaching powder Bleaching powder 0.125 kg 100 per kg 100 12.5
3 Ordinary labour T & P, sundries etc. 1 LS 550 per day 27.5 27.5
Sub-Total 160
Contractor's Profit 10% 0.1 16
Contractor's Overhead Expenses 3.5% 0.035 5.6
Total 181.6
Add VAT with adjustment factor. 1.08108 7.5% 0.075 14.72
Grand Total 196.32
Rate per sqm 19.6
Rate per sqm 19.6