32.10 Taking out and relaying of old brick soling including replacement of 10% brick

Considering 10 sqm of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mason / Mosaic mistry Mason 0.2 no 700 per day 700 140
2 Ordinary labour Ordinary labour 0.75 nos 550 per day 550 412.5
3 Sand (F.M. 0.8) Local sand (F.M. 0.8) 0.14 cum 1670 per % cft 589.18 82.49
4 1st class/Picked jhama standard bricks Add cost of around 10% bricks 30 nos 10000 per % 0 nos 10 300
5 Ordinary labour Cleaning, sorting and stacking bricks 1 LS 550 per day 82.5 82.5
6 Ordinary labour T & P, sundries 1 LS 550 per day 27.5 27.5
Sub-Total 1044.99
Contractor's Profit 10% 0.1 104.5
Contractor's Overhead Expenses 3.5% 0.035 36.57
Total 1186.06
Add VAT with adjustment factor. 1.08108 7.5% 0.075 96.17
Grand Total 1282.23
Rate per sqm 128.2
Rate per sqm 128.2