Considering 10 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Mason / Mosaic mistry Mason | 0.2 | no | 700 | per day | 700 | 140 | |
| 2 | Ordinary labour Ordinary labour | 0.75 | nos | 550 | per day | 550 | 412.5 | |
| 3 | Sand (F.M. 0.8) Local sand (F.M. 0.8) | 0.05 | cum | 1670 | per % cft | 589.18 | 29.46 | |
| 4 | Ordinary labour Cleaning, sorting and stacking bricks | 1 | LS | 550 | per day | 82.5 | 82.5 | |
| 5 | Ordinary labour T & P, sundries | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| Sub-Total | 691.96 | |||||||
| Contractor's Profit | 10% | 0.1 | 69.2 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 24.22 | |||||
| Total | 785.38 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 63.68 | ||||
| Grand Total | 849.06 | |||||||
| Rate per sqm | 84.9 | |||||||
| Rate per sqm | 84.9 | |||||||