32.11 Taking out and relaying of brick soling after redressing the surfaces

Considering 10 sqm of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mason / Mosaic mistry Mason 0.2 no 700 per day 700 140
2 Ordinary labour Ordinary labour 0.75 nos 550 per day 550 412.5
3 Sand (F.M. 0.8) Local sand (F.M. 0.8) 0.05 cum 1670 per % cft 589.18 29.46
4 Ordinary labour Cleaning, sorting and stacking bricks 1 LS 550 per day 82.5 82.5
5 Ordinary labour T & P, sundries 1 LS 550 per day 27.5 27.5
Sub-Total 691.96
Contractor's Profit 10% 0.1 69.2
Contractor's Overhead Expenses 3.5% 0.035 24.22
Total 785.38
Add VAT with adjustment factor. 1.08108 7.5% 0.075 63.68
Grand Total 849.06
Rate per sqm 84.9
Rate per sqm 84.9