Breakup

31.12.2 Taking out of old brick on edge pavement and restting Herring bone bond and redressing the surface

Considering 10 sqm of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mason / Mosaic mistry Mason 0.25 no 700 per day 700 175
2 Ordinary labour Ordinary labour 1.5 nos 550 per day 550 825
3 Sand (F.M. 0.8) Local sand (F.M. 0.8) 0.05 cum 1670 per % cft 589.18 29.46
4 Ordinary labour Cleaning, sorting and stacking bricks 1 LS 550 per day 55 55
5 Ordinary labour T & P, sundries 1 LS 550 per day 44 44
Sub-Total 1128.46
Contractor's Profit 10% 0.1 112.85
Contractor's Overhead Expenses 3.5% 0.035 39.5
Total 1280.81
Add VAT with adjustment factor. 1.08108 7.5% 0.075 103.85
Grand Total 1384.66
Rate per sqm 138.5
Rate per sqm 138.5