Considering 10 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour Skilled labour | 1 | no | 600 | per day | 600 | 600 | |
| 2 | Ordinary labour Cleaning, brooming etc. | 1 | LS | 550 | per day | 82.5 | 82.5 | |
| 3 | Ordinary labour T & P, scaffolding & sundries | 1 | LS | 550 | per day | 11 | 11 | |
| Sub-Total | 693.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 69.35 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 24.27 | |||||
| Total | 787.12 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 63.82 | ||||
| Grand Total | 850.94 | |||||||
| Rate per sqm | 85.1 | |||||||
| Rate per sqm | 85.1 | |||||||