Breakup

32.14 Supplying and fitting-fixing of wind tie with M.S. Flat bar clamp

Considering 30 m of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 M.S. plain bar and F.I. bar (non-structural use) 1.5" x 3/16" F.I. Bar in/c 5% wastage 44.75 kg 70000 per M. ton 70 3132.5
2 Grade 500(500Mpa), BDS-6935-2016 and ratio fy to fu => 1.25 6 mm dia M.S. rod in/c 5% wastage 1.6 kg 68000 per M. ton 68 108.8
3 Ordinary labour Cost of making hole in F.I. Bar 41 nos 550 per day 8.25 338.25
4 Ordinary labour Making J-hook in/c threading & washer and nuts 41 nos 550 per day 11 451
5 Ordinary labour Labour for fitting-fixing 1 LS 550 per day 522.5 522.5
6 Ordinary labour T & P, scaffolding & sundries 1 LS 550 per day 55 55
Sub-Total 4608.05
Contractor's Profit 10% 0.1 460.81
Contractor's Overhead Expenses 3.5% 0.035 161.28
Total 5230.14
Add VAT with adjustment factor. 1.08108 7.5% 0.075 424.06
Grand Total 5654.2
Rate per meter 188.47
Rate per meter 188.47