Considering 30 m of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | M.S. plain bar and F.I. bar (non-structural use) 1.5" x 3/16" F.I. Bar in/c 5% wastage | 44.75 | kg | 70000 | per M. ton | 70 | 3132.5 | |
| 2 | Grade 500(500Mpa), BDS-6935-2016 and ratio fy to fu => 1.25 6 mm dia M.S. rod in/c 5% wastage | 1.6 | kg | 68000 | per M. ton | 68 | 108.8 | |
| 3 | Ordinary labour Cost of making hole in F.I. Bar | 41 | nos | 550 | per day | 8.25 | 338.25 | |
| 4 | Ordinary labour Making J-hook in/c threading & washer and nuts | 41 | nos | 550 | per day | 11 | 451 | |
| 5 | Ordinary labour Labour for fitting-fixing | 1 | LS | 550 | per day | 522.5 | 522.5 | |
| 6 | Ordinary labour T & P, scaffolding & sundries | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 4608.05 | |||||||
| Contractor's Profit | 10% | 0.1 | 460.81 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 161.28 | |||||
| Total | 5230.14 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 424.06 | ||||
| Grand Total | 5654.2 | |||||||
| Rate per meter | 188.47 | |||||||
| Rate per meter | 188.47 | |||||||