32.17 Taking out of old & unserviceable wooden chowkat /door or window frame

Considering 1 No. Chowkat

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.4 no 600 per day 600 240
2 Ordinary labour T & P, cutting clamp, and removing screws & sundries 1 LS 550 per day 27.5 27.5
Sub-Total 267.5
Contractor's Profit 10% 0.1 26.75
Contractor's Overhead Expenses 3.5% 0.035 9.36
Total 303.61
Add VAT with adjustment factor. 1.08108 7.5% 0.075 24.62
Grand Total 328.23
Rate per each 328
Rate per each 328