Considering 1 No. Chowkat
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour Skilled labour | 0.4 | no | 600 | per day | 600 | 240 | |
| 2 | Ordinary labour T & P, cutting clamp, and removing screws & sundries | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| 3 | Mason / Mosaic mistry Labour for re-fitting or refixing in position : Mason | 0.25 | no | 700 | per day | 700 | 175 | |
| 4 | Ordinary labour Ordinary labour | 0.25 | no | 550 | per day | 550 | 137.5 | |
| 5 | Carpenter Carpenter for repair | 0.25 | no | 700 | per day | 700 | 175 | |
| 6 | Ordinary labour Screws | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| 7 | Ordinary labour Paint on clamp & side of Chowkat in contact woth wall | 1 | LS | 550 | per day | 44 | 44 | |
| 8 | Ordinary labour T & P, sundries etc. | 1 | LS | 550 | per day | 35.75 | 35.75 | |
| Sub-Total | 862.25 | |||||||
| Contractor's Profit | 10% | 0.1 | 86.23 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 30.18 | |||||
| Total | 978.66 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 79.35 | ||||
| Grand Total | 1058.01 | |||||||
| Rate per each | 1058 | |||||||
| Rate per each | 1058 | |||||||