Breakup

32.18 Taking out of old wooden chowkat/door or window frame and refitting and refixing after minor repair (excluding the cost of wood and M.S. clamp)

Considering 1 No. Chowkat

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.4 no 600 per day 600 240
2 Ordinary labour T & P, cutting clamp, and removing screws & sundries 1 LS 550 per day 27.5 27.5
3 Mason / Mosaic mistry Labour for re-fitting or refixing in position : Mason 0.25 no 700 per day 700 175
4 Ordinary labour Ordinary labour 0.25 no 550 per day 550 137.5
5 Carpenter Carpenter for repair 0.25 no 700 per day 700 175
6 Ordinary labour Screws 1 LS 550 per day 27.5 27.5
7 Ordinary labour Paint on clamp & side of Chowkat in contact woth wall 1 LS 550 per day 44 44
8 Ordinary labour T & P, sundries etc. 1 LS 550 per day 35.75 35.75
Sub-Total 862.25
Contractor's Profit 10% 0.1 86.23
Contractor's Overhead Expenses 3.5% 0.035 30.18
Total 978.66
Add VAT with adjustment factor. 1.08108 7.5% 0.075 79.35
Grand Total 1058.01
Rate per each 1058
Rate per each 1058