Breakup

32.19 Taking out and refitting of wooden shutter after easing excluding the cost of wood

Considering 1.07 m x 2.13 m = 2.28 sqm

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Carpenter Carpenter 0.5 no 700 per day 700 350
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 0.75 no 550 per day 550 412.5
3 25 mm iron screw Screws 2 dzns 9 dz 9 18
4 Ordinary labour T & P, nails, glues sundries etc. 1 LS 550 per day 55 55
Sub-Total 835.5
Contractor's Profit 10% 0.1 83.55
Contractor's Overhead Expenses 3.5% 0.035 29.24
Total 948.29
Add VAT with adjustment factor. 1.08108 7.5% 0.075 76.89
Grand Total 1025.18
Rate per sqm 449.56
Rate per sqm 449.56