Breakup

32.20.1 Thorough repairs to wooden door and window Pannel shutter excluding the cost of wood

Considering 1.83 m x 1.07 m =1.96 sqm pannel shutter

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Carpenter Carpenter 1 no 700 per day 700 700
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 1 no 550 per day 550 550
3 25 mm iron screw Screws 4 dzns 9 dz 9 36
4 Ordinary labour T & P, nails, glue sundries etc. 1 LS 550 per day 55 55
Sub-Total 1341
Contractor's Profit 10% 0.1 134.1
Contractor's Overhead Expenses 3.5% 0.035 46.94
Total 1522.04
Add VAT with adjustment factor. 1.08108 7.5% 0.075 123.41
Grand Total 1645.45
Rate per sqm 839.29
Rate per sqm 839.29
Help