Breakup

32.20.2 Thorough repairs to wooden door and window Batten shutter excluding the cost of wood

Considering 2.057 m x 1.067 m = 2.194 sqm batten shutter

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Carpenter Carpenter 0.75 no 700 per day 700 525
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 0.75 no 550 per day 550 412.5
3 25 mm iron screw Screws 9 dzns 9 dz 9 81
4 Ordinary labour T & P, nails, glue sundries etc. 1 LS 550 per day 55 55
Sub-Total 1073.5
Contractor's Profit 10% 0.1 107.35
Contractor's Overhead Expenses 3.5% 0.035 37.57
Total 1218.42
Add VAT with adjustment factor. 1.08108 7.5% 0.075 98.79
Grand Total 1317.21
Rate per sqm 600.27
Rate per sqm 600.27