32.20.3 Thorough repairs to wooden door and window Venetian shutter excluding the cost of wood

Considering 2.057 m x 1.067 m = 2.194 sqm venetian shutter

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Carpenter Carpenter 1 no 700 per day 700 700
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 1 no 550 per day 550 550
3 25 mm iron screw Screws 5 dz 9 dz 9 45
4 Ordinary labour T & P, nails, glue sundries etc. 1 LS 550 per day 55 55
Sub-Total 1350
Contractor's Profit 10% 0.1 135
Contractor's Overhead Expenses 3.5% 0.035 47.25
Total 1532.25
Add VAT with adjustment factor. 1.08108 7.5% 0.075 124.24
Grand Total 1656.49
Rate per sqm 754.79
Rate per sqm 754.79