Breakup

32.20.4 Thorough repairs to wooden door and window Glazed shutter excluding the cost of glass & wood

Considering 1.297 sqm of glazed shutter

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Carpenter Carpenter 0.5 no 700 per day 700 350
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 0.5 no 550 per day 550 275
3 25 mm iron screw Screws 2 dz 9 dz 9 18
4 Ordinary labour T & P, glue, nails, sundries etc. 1 LS 550 per day 55 55
Sub-Total 698
Contractor's Profit 10% 0.1 69.8
Contractor's Overhead Expenses 3.5% 0.035 24.43
Total 792.23
Add VAT with adjustment factor. 1.08108 7.5% 0.075 64.23
Grand Total 856.46
Rate per sqm 659.98
Rate per sqm 659.98