Considering 1.297 sqm of glazed shutter
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Carpenter Carpenter | 0.5 | no | 700 | per day | 700 | 350 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter | 0.5 | no | 550 | per day | 550 | 275 | |
| 3 | 25 mm iron screw Screws | 2 | dz | 9 | dz | 9 | 18 | |
| 4 | Ordinary labour T & P, glue, nails, sundries etc. | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 698 | |||||||
| Contractor's Profit | 10% | 0.1 | 69.8 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 24.43 | |||||
| Total | 792.23 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 64.23 | ||||
| Grand Total | 856.46 | |||||||
| Rate per sqm | 659.98 | |||||||
| Rate per sqm | 659.98 | |||||||