Considering 1 sqm of 3 mm glass in wooden frame
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 3 mm thick clear glass Cost of glass in/c 15% wastage | 1.05 | sqm | 50 | per sft | 538 | 564.9 | |
| 2 | 3 mm thick clear glass Cost of bead and putty | 1.05 | LS | 50 | per sft | 47.6 | 49.98 | |
| 3 | Ordinary labour Labour for cleaning | 1 | LS | 550 | per day | 82.5 | 82.5 | |
| 4 | Ordinary labour Labour for fitting-fixing | 1 | LS | 550 | per day | 110 | 110 | |
| 5 | Ordinary labour T & P, sundries etc. | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| Sub-Total | 834.88 | |||||||
| Contractor's Profit | 10% | 0.1 | 83.49 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 29.22 | |||||
| Total | 947.59 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 76.83 | ||||
| Grand Total | 1024.42 | |||||||
| Rate per sqm | 1024 | |||||||
| Rate per sqm | 1024 | |||||||