Breakup

32.21.2 Renewing of 3 mm glass panes in steel frame including supply of glass

Considering 1 sqm of 3 mm glass in steel frame

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 3 mm thick clear glass Cost of glass in/c 15% wastage 1.05 sqm 50 per sft 538 564.9
2 3 mm thick clear glass Cost of bead and putty 1.05 LS 50 per sft 47.6 49.98
3 Ordinary labour Labour for cleaning 1 LS 550 per day 82.5 82.5
4 Ordinary labour Labour for fitting-fixing 1 LS 550 per day 110 110
5 Ordinary labour T & P, sundries etc. 1 LS 550 per day 27.5 27.5
Sub-Total 834.88
Contractor's Profit 10% 0.1 83.49
Contractor's Overhead Expenses 3.5% 0.035 29.22
Total 947.59
Add VAT with adjustment factor. 1.08108 7.5% 0.075 76.83
Grand Total 1024.42
Rate per sqm 1024
Rate per sqm 1024