Considering 1 sqm of 5 mm glass in steel frame
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 5 mm clear glass Cost of glass in/c 15% wastage | 1.05 | sqm | 71 | sft | 878.55 | 922.48 | |
| 2 | 5 mm clear glass Cost of bead and putty /neoprene/sealant | 1.05 | LS | 71 | sft | 91.34 | 95.91 | |
| 3 | Ordinary labour Labour | 1 | LS | 550 | per day | 137.5 | 137.5 | |
| 4 | Ordinary labour T & P, sundries etc. | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 1210.89 | |||||||
| Contractor's Profit | 10% | 0.1 | 121.09 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 42.38 | |||||
| Total | 1374.36 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 111.43 | ||||
| Grand Total | 1485.79 | |||||||
| Rate per sqm | 1486 | |||||||
| Rate per sqm | 1486 | |||||||