Breakup

32.24.1 Replacing / renewing of fly proof wire net (with all new materials) the excluding cost of wood

Considering 2 m x 2 m = 4 sqm of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Fly proof wire-net Net in/c lap & wastage 4.5 sqm 100 per sqm 100 450
2 25 mm iron screw Nails, screws etc. 1 LS 9 dz 37.5 37.5
3 75 mm - 150 mm M.S. clamp 6" long clamps 4 nos 32 each 32 128
4 Carpenter Labour charge for fitting-fixing 4 sqm 700 per day 437.5 1750
5 Ordinary labour T & P, scaffolding & sundries 1 LS 550 per day 137.5 137.5
Sub-Total 2503
Contractor's Profit 10% 0.1 250.3
Contractor's Overhead Expenses 3.5% 0.035 87.61
Total 2840.91
Add VAT with adjustment factor. 1.08108 7.5% 0.075 230.34
Grand Total 3071.25
Rate per sqm 767.75
Rate per sqm 767.75