Considering 1 m x 1.5 m = 1.5 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Fly proof wire-net Net in/c wastage | 1.75 | sqm | 100 | per sqm | 100 | 175 | |
| 2 | 25 mm iron screw Nails, screws etc. | 1 | LS | 9 | dz | 15 | 15 | |
| 3 | Carpenter Labour charge | 1.5 | sqm | 700 | per day | 350 | 525 | |
| 4 | Ordinary labour T & P, scaffolding & sundries | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 770 | |||||||
| Contractor's Profit | 10% | 0.1 | 77 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 26.95 | |||||
| Total | 873.95 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 70.86 | ||||
| Grand Total | 944.81 | |||||||
| Rate per sqm | 630 | |||||||
| Rate per sqm | 630 | |||||||