Breakup

32.27 Taking out of hard board ceiling, walling

Considering 10 sqm of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Carpenter Carpenter 0.12 no 700 per day 700 84
2 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 0.12 no 550 per day 550 66
3 Ordinary labour T & P, scaffolding, sundries etc. 1 LS 550 per day 25.78 25.78
Sub-Total 175.78
Contractor's Profit 10% 0.1 17.58
Contractor's Overhead Expenses 3.5% 0.035 6.15
Total 199.51
Add VAT with adjustment factor. 1.08108 7.5% 0.075 16.18
Grand Total 215.69
Rate per sqm 21.6
Rate per sqm 21.6