Considering 10 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Carpenter Carpenter | 0.12 | no | 700 | per day | 700 | 84 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter | 0.12 | no | 550 | per day | 550 | 66 | |
| 3 | Ordinary labour T & P, scaffolding, sundries etc. | 1 | LS | 550 | per day | 25.78 | 25.78 | |
| Sub-Total | 175.78 | |||||||
| Contractor's Profit | 10% | 0.1 | 17.58 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 6.15 | |||||
| Total | 199.51 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 16.18 | ||||
| Grand Total | 215.69 | |||||||
| Rate per sqm | 21.6 | |||||||
| Rate per sqm | 21.6 | |||||||