Considering 2.44 m x 1.22 m = 2.98 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 2.44 m x 1.22 m size hard board Hard board in/c wastage | 1.05 | no | 600 | per piece | 600 | 630 | |
| 2 | 25 mm iron screw Nails, screws, clamps etc. | 1 | LS | 9 | dz | 45 | 45 | |
| 3 | Carpenter Labour charge | 2.98 | sqm | 700 | per day | 262.5 | 782.25 | |
| 4 | Ordinary labour T & P, scaffolding & sundries | 1 | LS | 550 | per day | 137.5 | 137.5 | |
| Sub-Total | 1594.75 | |||||||
| Contractor's Profit | 10% | 0.1 | 159.48 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 55.82 | |||||
| Total | 1810.05 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 146.76 | ||||
| Grand Total | 1956.81 | |||||||
| Rate per sqm | 656.71 | |||||||
| Rate per sqm | 656.71 | |||||||