32.28 Renewing of hard board ceiling or walling excluding cost of wood

Considering 2.44 m x 1.22 m = 2.98 sqm of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 2.44 m x 1.22 m size hard board Hard board in/c wastage 1.05 no 600 per piece 600 630
2 25 mm iron screw Nails, screws, clamps etc. 1 LS 9 dz 45 45
3 Carpenter Labour charge 2.98 sqm 700 per day 262.5 782.25
4 Ordinary labour T & P, scaffolding & sundries 1 LS 550 per day 137.5 137.5
Sub-Total 1594.75
Contractor's Profit 10% 0.1 159.48
Contractor's Overhead Expenses 3.5% 0.035 55.82
Total 1810.05
Add VAT with adjustment factor. 1.08108 7.5% 0.075 146.76
Grand Total 1956.81
Rate per sqm 656.71
Rate per sqm 656.71