Breakup

32.29 Replacing of wooden cleat, making, finishing and fixing with chowkat by means of 40 mm hinge

Considering 1 No. cleat

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Chattogram teak Timber (approved) 1 LS 4400 per cft 25.14 25.14
2 38 mm iron hinge 1.5" iron hinge 1 no 5 each 5 5
3 25 mm iron screw Screw 4 no 9 dz 0.75 3
4 Foreman/Supervisor Labour charge in/c polishing/painting etc 1 LS 850 per day 31.88 31.88
Sub-Total 65.02
Contractor's Profit 10% 0.1 6.5
Contractor's Overhead Expenses 3.5% 0.035 2.2800000000000002
Total 73.8
Add VAT with adjustment factor. 1.08108 7.5% 0.075 5.98
Grand Total 79.78
Rate per each 80
Rate per each 80