Considering 1 No. cleat
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Chattogram teak Timber (approved) | 1 | LS | 4400 | per cft | 25.14 | 25.14 | |
| 2 | 38 mm iron hinge 1.5" iron hinge | 1 | no | 5 | each | 5 | 5 | |
| 3 | 25 mm iron screw Screw | 4 | no | 9 | dz | 0.75 | 3 | |
| 4 | Foreman/Supervisor Labour charge in/c polishing/painting etc | 1 | LS | 850 | per day | 31.88 | 31.88 | |
| Sub-Total | 65.02 | |||||||
| Contractor's Profit | 10% | 0.1 | 6.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2.2800000000000002 | |||||
| Total | 73.8 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 5.98 | ||||
| Grand Total | 79.78 | |||||||
| Rate per each | 80 | |||||||