Considering 1 No. cleat
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Chattogram teak Timber (approved) | 1 | LS | 4400 | per cft | 25.14 | 25.14 | |
| 2 | 38 mm brass hinge 1.5" brass hinge | 1 | no | 7 | each | 7 | 7 | |
| 3 | 25 mm brass screw Screw | 4 | no | 16 | dz | 1.33 | 5.32 | |
| 4 | Carpenter Labour charge in/c polishing/painting etc | 1 | LS | 700 | per day | 35 | 35 | |
| Sub-Total | 72.46 | |||||||
| Contractor's Profit | 10% | 0.1 | 7.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2.54 | |||||
| Total | 82.25 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 6.67 | ||||
| Grand Total | 88.92 | |||||||
| Rate per each | 89 | |||||||
| Rate per each | 89 | |||||||