Breakup

32.30 Replacing of cleat with brass hinge

Considering 1 No. cleat

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Chattogram teak Timber (approved) 1 LS 4400 per cft 25.14 25.14
2 38 mm brass hinge 1.5" brass hinge 1 no 7 each 7 7
3 25 mm brass screw Screw 4 no 16 dz 1.33 5.32
4 Carpenter Labour charge in/c polishing/painting etc 1 LS 700 per day 35 35
Sub-Total 72.46
Contractor's Profit 10% 0.1 7.25
Contractor's Overhead Expenses 3.5% 0.035 2.54
Total 82.25
Add VAT with adjustment factor. 1.08108 7.5% 0.075 6.67
Grand Total 88.92
Rate per each 89
Rate per each 89