32.31 Replacing of wooden buffer block

Considering 1 No. buffer block (150 x 65 x 38 mm)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Chattogram teak Timber (approved) 1 LS 4400 per cft 24.05 24.05
2 50 mm iron screw 2" Screw 2 no 16 dz 1.33 2.66
3 Carpenter Labour charge in/c polishing/painting etc 1 LS 700 per day 21.88 21.88
Sub-Total 48.59
Contractor's Profit 10% 0.1 4.86
Contractor's Overhead Expenses 3.5% 0.035 1.7
Total 55.15
Add VAT with adjustment factor. 1.08108 7.5% 0.075 4.47
Grand Total 59.62