Considering 1 No. buffer block (150 x 65 x 38 mm)
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Chattogram teak Timber (approved) | 1 | LS | 4400 | per cft | 24.05 | 24.05 | |
| 2 | 50 mm iron screw 2" Screw | 2 | no | 16 | dz | 1.33 | 2.66 | |
| 3 | Carpenter Labour charge in/c polishing/painting etc | 1 | LS | 700 | per day | 21.88 | 21.88 | |
| Sub-Total | 48.59 | |||||||
| Contractor's Profit | 10% | 0.1 | 4.86 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1.7 | |||||
| Total | 55.15 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 4.47 | ||||
| Grand Total | 59.62 | |||||||
| Rate per each | 60 | |||||||
| Rate per each | 60 | |||||||