Breakup

32.32 Replacig of wooden catcher block

Considering 1 No. of block (50 x 50 x 75 mm)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Chattogram teak Timber (approved) 1 LS 4400 per cft 37.71 37.71
2 25 mm iron screw Iron cleat & screws 1 LS 9 dz 9.45 9.45
3 Carpenter Labour charge in/c polishing/painting etc 1 LS 700 per day 21.88 21.88
4 Carpenter Sundries 1 LS 700 per day 2.8 2.8
Sub-Total 71.84
Contractor's Profit 10% 0.1 7.18
Contractor's Overhead Expenses 3.5% 0.035 2.51
Total 81.53
Add VAT with adjustment factor. 1.08108 7.5% 0.075 6.61
Grand Total 88.14
Rate per each 88
Rate per each 88