Considering 1 No. hook
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 100 mm long catch hook 100 mm long catch hook | 1 | no | 7 | each | 7 | 7 | |
| 2 | Carpenter Labour charge | 1 | LS | 700 | per day | 8.75 | 8.75 | |
| Sub-Total | 15.75 | |||||||
| Contractor's Profit | 10% | 0.1 | 1.58 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 0.55 | |||||
| Total | 17.88 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1.45 | ||||
| Grand Total | 19.33 | |||||||
| Rate per each | 19 | |||||||
| Rate per each | 19 | |||||||