32.33.4 Replacing of 200 mm long galvanized iron catch hook

Considering 1 No. hook

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 200 mm long catch hook 200 mm long catch hook 1 no 11 each 11 11
2 Carpenter Labour charge 1 LS 700 per day 8.75 8.75
Sub-Total 19.75
Contractor's Profit 10% 0.1 1.98
Contractor's Overhead Expenses 3.5% 0.035 0.69
Total 22.42
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1.8199999999999998
Grand Total 24.24
Rate per each 24