Breakup

32.33.5 Replacing of 225 mm long galvanized iron catch hook

Considering 1 No. hook

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 225 mm long catch hook 225 mm long catch hook 1 no 17 each 17 17
2 Carpenter Labour charge 1 LS 700 per day 8.75 8.75
Sub-Total 25.75
Contractor's Profit 10% 0.1 2.58
Contractor's Overhead Expenses 3.5% 0.035 0.9
Total 29.23
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2.37
Grand Total 31.6
Rate per each 32
Rate per each 32