6th to 9th floor
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Built-up MS Sections Cost of steel frame | 5000 | kg | 111.48 | per kg | 111.48 | 557400 | |
| 2 | Cost of motor, car, gear box, push button, cable and necessary safety measures | LS | 500000 | |||||
| 3 | a) RCC base construction of size 2.5 m x 2.5 m x 0.45 m= | LS | 42187.5 | |||||
| 4 | b) Connection with anchor bolts at every floor, 4- bolts per floor) | LS | 10000 | |||||
| 5 | c) Installation and commissioning | LS | 50000 | |||||
| 6 | Dismantling charge | LS | 30000 | |||||
| 7 | a) Trained operator | LS | 17610 | |||||
| 8 | b) Maintenance & Electricity bill | LS | 2000 | |||||
| Sub-Total | 1209197.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 120919.75 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 42321.91 | |||||
| Total | 1372439.16 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 111278.74 | ||||
| Grand Total | 1483717.9 | |||||||
| Rate per month | 1483718 | |||||||
| Rate per month | 1483718 | |||||||