Breakup

01.11.1 6th to 9th floor, hoisting speed 40 m/min

6th to 9th floor

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Built-up MS Sections Cost of steel frame 5000 kg 111.48 per kg 111.48 557400
2 Cost of motor, car, gear box, push button, cable and necessary safety measures LS 500000
3 a) RCC base construction of size 2.5 m x 2.5 m x 0.45 m= LS 42187.5
4 b) Connection with anchor bolts at every floor, 4- bolts per floor) LS 10000
5 c) Installation and commissioning LS 50000
6 Dismantling charge LS 30000
7 a) Trained operator LS 17610
8 b) Maintenance & Electricity bill LS 2000
Sub-Total 1209197.5
Contractor's Profit 10% 0.1 120919.75
Contractor's Overhead Expenses 3.5% 0.035 42321.91
Total 1372439.16
Add VAT with adjustment factor. 1.08108 7.5% 0.075 111278.74
Grand Total 1483717.9
Rate per month 1483718
Rate per month 1483718