Considering 1 No. iron ring
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 mm dia iron ring 50 mm dia iron ring | 1 | no | 15 | each | 15 | 15 | |
| 2 | Carpenter Labour charge | 1 | LS | 700 | per day | 10.94 | 10.94 | |
| Sub-Total | 25.94 | |||||||
| Contractor's Profit | 10% | 0.1 | 2.59 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 0.91 | |||||
| Total | 29.44 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 2.39 | ||||
| Grand Total | 31.83 | |||||||
| Rate per each | 32 | |||||||
| Rate per each | 32 | |||||||