Considering 1 No. brass hinge
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 mm dia brass ring 50 mm dia brass ring | 1 | no | 42 | each | 42 | 42 | |
| 2 | Carpenter Labour charge | 1 | LS | 700 | per day | 10.94 | 10.94 | |
| Sub-Total | 52.94 | |||||||
| Contractor's Profit | 10% | 0.1 | 5.29 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1.85 | |||||
| Total | 60.08 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 4.87 | ||||
| Grand Total | 64.95 | |||||||
| Rate per each | 65 | |||||||
| Rate per each | 65 | |||||||