Breakup

32.40.1 Supplying, fitting and fixing of 25 x 25 mm expanded mesh metal net of wooden or steel frame (excluding the cost of wood or steel sections and painting)

Considering 1.83 x 1.83 m = 3.35 sqm of work excluding cost of frame

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 25 mm expanded metal net 25 mm x 25 mesh of expanded mesh metal net in/c wastage, lap etc. 3.8 sqm 120 per sqm 120 456
2 25 mm iron screw Nails, screws etc. 1 LS 9 dz 37.5 37.5
3 100 mm x 38 mm x 6 mm size clamp 4"x 1.5" x 1/8" size clamp 4 nos 16 each 12 48
4 Carpenter Labour charge in/c fitting-fixing in position 3.35 sqm / LS 700 per day 700 2345
5 Ordinary labour T & P, scaffolding & sundries 1 LS 550 per day 137.5 137.5
Sub-Total 3024
Contractor's Profit 10% 0.1 302.4
Contractor's Overhead Expenses 3.5% 0.035 105.84
Total 3432.24
Add VAT with adjustment factor. 1.08108 7.5% 0.075 278.29
Grand Total 3710.53
Rate per sqm 1107.76
Rate per sqm 1107.76