Considering 1.83 x 1.83 m = 3.35 sqm of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 25 mm expanded metal net 1" expanded mesh metal net | 3.8 | sqm | 120 | per sqm | 120 | 456 | |
| 2 | 100 mm x 38 mm x 6 mm size clamp 4"x 1.5" x 1/8" size clamp | 4 | nos | 16 | each | 16 | 64 | |
| 3 | Welder Welding, reveting etc. | 1 | LS | 700 | per day | 350 | 350 | |
| 4 | M.S. plain bar and F.I. bar (non-structural use) 1" x 0.25" F.I. Bar : (12 x 6'-0"=72rft + '@ 0.85 Ibs per rft=61.20lbs + Add 5% wastage = 3.06lbs)=64.26lbs | 64.26 | lbs | 70000 | per M. ton | 31.75 | 2040.26 | |
| 5 | Carpenter Labour charge for making & fitting-fixing | 3.35 | sqm/LS | 700 | per day | 787.5 | 2638.13 | |
| 6 | Ordinary labour T & P, local carriage, sundries | 1 | LS | 550 | per day | 137.5 | 137.5 | |
| Sub-Total | 5685.89 | |||||||
| Contractor's Profit | 10% | 0.1 | 568.59 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 199.01 | |||||
| Total | 6453.49 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 523.26 | ||||
| Grand Total | 6976.75 | |||||||
| Rate per sqm | 2082.69 | |||||||
| Rate per sqm | 2082.69 | |||||||