Materials for considering 100 sqm of work for 3 coats
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Slaked lime Materials for considering 100 sqm of work for 3 coats : Slaked lime | 20.08 | kg | 25 | per kg | 25 | 502 | |
| 2 | Gum Gum | 0.32 | kg | 200 | per kg | 200 | 64 | |
| 3 | Blue Blue | 0.22 | kg | 200 | per kg | 200 | 44 | |
| 4 | Mason / Mosaic mistry Mason for mending good the holes, patch etc. | 0.1 | no | 700 | per day | 700 | 70 | |
| 5 | Painter Painter | 0.5 | no | 700 | per day | 700 | 350 | |
| 6 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| 7 | Ordinary labour Ladder, sundries, local carriage etc. | 1 | LS | 550 | per day | 110 | 110 | |
| 8 | Ordinary labour Cleaning spot mark, brooming, scraping from the old surface, clearin space etc. | 1 | LS | 550 | per day | 165 | 165 | |
| Sub-Total | 1580 | |||||||
| Contractor's Profit | 10% | 0.1 | 158 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 55.3 | |||||
| Total | 1793.3 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 145.4 | ||||
| Grand Total | 1938.7 | |||||||
| Rate per sqm | 19.39 | |||||||
| Rate per sqm | 19.39 | |||||||