Breakup

32.41.1 Renewing of white washing: 1 coat

Materials for considering 100 sqm of work for 3 coats

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Slaked lime Materials for considering 100 sqm of work for 3 coats : Slaked lime 20.08 kg 25 per kg 25 502
2 Gum Gum 0.32 kg 200 per kg 200 64
3 Blue Blue 0.22 kg 200 per kg 200 44
4 Mason / Mosaic mistry Mason for mending good the holes, patch etc. 0.1 no 700 per day 700 70
5 Painter Painter 0.5 no 700 per day 700 350
6 Ordinary labour Ordinary labour 0.5 no 550 per day 550 275
7 Ordinary labour Ladder, sundries, local carriage etc. 1 LS 550 per day 110 110
8 Ordinary labour Cleaning spot mark, brooming, scraping from the old surface, clearin space etc. 1 LS 550 per day 165 165
Sub-Total 1580
Contractor's Profit 10% 0.1 158
Contractor's Overhead Expenses 3.5% 0.035 55.3
Total 1793.3
Add VAT with adjustment factor. 1.08108 7.5% 0.075 145.4
Grand Total 1938.7
Rate per sqm 19.39
Rate per sqm 19.39