Considering 100 sqm of work for 1 coat
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Slaked lime Materials for considering 100 sqm of work for 3 coats : Slaked lime | 20.08 | kg | 25 | per kg | 25 | 502 | |
| 2 | Gum Gum | 0.32 | kg | 200 | per kg | 200 | 64 | |
| Sub-Total | 566 | |||||||
| Contractor's Profit | 10% | 0.1 | 56.6 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 19.81 | |||||
| Total | 642.41 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 52.09 | ||||
| Grand Total | 694.5 | |||||||
| Rate per sqm | 6.95 | |||||||
| Rate per sqm | 6.95 | |||||||