32.42.1 Renewing of colour washing with yellow ochre: 1 coat

Considering 100 sqm of work for 1 coat

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Slaked lime Materials for considering 100 sqm of work for 3 coats : Slaked lime 20.08 kg 25 per kg 25 502
2 Gum Gum 0.32 kg 200 per kg 200 64
Sub-Total 566
Contractor's Profit 10% 0.1 56.6
Contractor's Overhead Expenses 3.5% 0.035 19.81
Total 642.41
Add VAT with adjustment factor. 1.08108 7.5% 0.075 52.09
Grand Total 694.5
Rate per sqm 6.95