Considering 100 sqm of work for 2 coats
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Slaked lime Slaked lime | 20.08 | kg | 25 | per kg | 25 | 502 | |
| 2 | Gum Gum | 0.32 | kg | 200 | per kg | 200 | 64 | |
| 3 | Blue Blue | 0.22 | kg | 200 | per kg | 200 | 44 | |
| Sub-Total | 610 | |||||||
| Contractor's Profit | 10% | 0.1 | 61 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 21.35 | |||||
| Total | 692.35 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 56.14 | ||||
| Grand Total | 748.49 | |||||||
| Rate per sqm | 7.48 | |||||||
| Rate per sqm | 7.48 | |||||||