Materials for considering 10 sqm of work for 2 coats
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Premium exterior emulsion paint Paint | 1 | liter | 430 | per litre | 430 | 430 | |
| 2 | Painter Painter | 0.5 | no | 700 | per day | 700 | 350 | |
| 3 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter | 0.5 | no | 550 | per day | 550 | 275 | |
| 4 | Ordinary labour Ordinary labour for cleaning surface | 0.5 | no | 550 | per day | 550 | 275 | |
| 5 | Ordinary labour Cleaning spot mark, brooming, scraping the old surface, clearing space, tools and plant, sundries etc | 1 | LS | 550 | per day | 110 | 110 | |
| Sub-Total | 1440 | |||||||
| Contractor's Profit | 10% | 0.1 | 144 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 50.4 | |||||
| Total | 1634.4 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 132.52 | ||||
| Grand Total | 1766.92 | |||||||
| Rate per sqm | 176.7 | |||||||
| Rate per sqm | 176.7 | |||||||