Considering 10 sqm of work for 2 coats
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Standard synthetic enamel paint Paint | 0.75 | liter | 220 | per litre | 220 | 165 | |
| 2 | Thinner for oil-based paint (turpentine) for general purpose Thinner | 0.5 | liter | 131 | per litre | 131 | 65.5 | |
| 3 | Painter Painter | 0.95 | no | 700 | per day | 700 | 665 | |
| 4 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| 5 | Ordinary labour Cleaning old surface in/c sand paper etc. | 1 | LS | 550 | per day | 44 | 44 | |
| Sub-Total | 1489.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 148.95 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 52.13 | |||||
| Total | 1690.58 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 137.07 | ||||
| Grand Total | 1827.65 | |||||||
| Rate per sqm | 182.8 | |||||||
| Rate per sqm | 182.8 | |||||||