Considering 10 sqm of work for 1 coat
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Acrylic plastic emulsion paint (plastic/matt finish) Paint | 0.7 | liter | 245 | per litre | 245 | 171.5 | |
| 2 | Painter Painter | 0.5 | no | 700 | per day | 700 | 350 | |
| 3 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter | 0.5 | no | 550 | per day | 550 | 275 | |
| 4 | Ordinary labour Scaffolding, sundries, local carriage etc. | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| 5 | Ordinary labour Cleaning old surface in/c sand paper etc. | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 879 | |||||||
| Contractor's Profit | 10% | 0.1 | 87.9 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 30.77 | |||||
| Total | 997.67 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 80.89 | ||||
| Grand Total | 1078.56 | |||||||
| Rate per sqm | 107.9 | |||||||