Breakup

32.49 Washing of painted wall surface with suitable soap or any other detergent

Considering 10 sqm of work for 1 coat

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Skilled labour 0.45 no 550 per day 550 247.5
2 Ordinary labour Detergent/soap 1 LS 550 per day 17.19 17.19
3 Ordinary labour Scaffolding, foam, water, sundries etc. 1 LS 550 per day 27.5 27.5
Sub-Total 292.19
Contractor's Profit 10% 0.1 29.22
Contractor's Overhead Expenses 3.5% 0.035 10.23
Total 331.64
Add VAT with adjustment factor. 1.08108 7.5% 0.075 26.89
Grand Total 358.53
Rate per sqm 35.9
Rate per sqm 35.9