Considering 10 sqm of work for 1 coat
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Skilled labour | 0.45 | no | 550 | per day | 550 | 247.5 | |
| 2 | Ordinary labour Detergent/soap | 1 | LS | 550 | per day | 17.19 | 17.19 | |
| 3 | Ordinary labour Scaffolding, foam, water, sundries etc. | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| Sub-Total | 292.19 | |||||||
| Contractor's Profit | 10% | 0.1 | 29.22 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 10.23 | |||||
| Total | 331.64 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 26.89 | ||||
| Grand Total | 358.53 | |||||||
| Rate per sqm | 35.9 | |||||||
| Rate per sqm | 35.9 | |||||||