Considering 10 sqm of work for 1 coat
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Chlorinated rubber paint Paint | 0.7 | liter | 638 | per litre | 638 | 446.6 | |
| 2 | Chlorinated rubber paint thinner Thinner | 0.42 | liter | 208 | per litre | 208 | 87.36 | |
| 3 | Painter Painter | 0.75 | no | 700 | per day | 700 | 525 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter | 0.75 | no | 550 | per day | 550 | 412.5 | |
| 5 | Ordinary labour Scaffolding, sundries, local carriage etc. | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| 6 | Ordinary labour Cleaning old surface in/c sand paper etc. | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 1553.96 | |||||||
| Contractor's Profit | 10% | 0.1 | 155.4 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 54.39 | |||||
| Total | 1763.75 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 143.01 | ||||
| Grand Total | 1906.76 | |||||||
| Rate per sqm | 190.7 | |||||||
| Rate per sqm | 190.7 | |||||||