Considering 10 sqm of work for 2 coats
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Chlorinated rubber paint Paint | 1 | liter | 638 | per litre | 638 | 638 | |
| 2 | Chlorinated rubber paint thinner Thinner | 0.6 | liter | 208 | per litre | 208 | 124.8 | |
| 3 | Painter Painter | 1 | no | 700 | per day | 700 | 700 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter | 1 | no | 550 | per day | 550 | 550 | |
| 5 | Ordinary labour Scaffolding, sundries, local carriage etc. | 1 | LS | 550 | per day | 55 | 55 | |
| 6 | Ordinary labour Cleaning old surface in/c sand paper etc. | 1 | LS | 550 | per day | 165 | 165 | |
| Sub-Total | 2232.8 | |||||||
| Contractor's Profit | 10% | 0.1 | 223.28 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 78.15 | |||||
| Total | 2534.23 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 205.48 | ||||
| Grand Total | 2739.71 | |||||||
| Rate per sqm | 274 | |||||||
| Rate per sqm | 274 | |||||||