Breakup

32.51.1 Renewing of french polishing: 1 coats

Considering 10 sqm of work for 1 coat

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials for french polishing: 3 coats on new surface Materials (40% of new surface) 1 sft 820 % sft 353.06 353.06
2 Painter Painter 0.5 no 700 per day 700 350
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter 0.5 no 550 per day 550 275
4 Ordinary labour Scaffolding, sundries, local carriage etc. 1 LS 550 per day 27.5 27.5
5 Ordinary labour Cleaning old surface in/c sand paper etc. 1 LS 550 per day 55 55
Sub-Total 1060.56
Contractor's Profit 10% 0.1 106.06
Contractor's Overhead Expenses 3.5% 0.035 37.12
Total 1203.74
Add VAT with adjustment factor. 1.08108 7.5% 0.075 97.6
Grand Total 1301.34
Rate per sqm 130.1
Rate per sqm 130.1