Breakup

32.51.2 Renewing of french polishing: 2 coat

Considering 10 sqm of work for 2 coats

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Materials for french polishing: 3 coats on new surface Materials (75% of new surface) 1 sft 820 % sft 661.99 661.99
2 Painter Painter 0.75 no 700 per day 700 525
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to painter 0.75 no 550 per day 550 412.5
4 Ordinary labour Scaffolding, sundries, local carriage etc. 1 LS 550 per day 55 55
5 Ordinary labour Cleaning old surface in/c sand paper etc. 1 LS 550 per day 165 165
Sub-Total 1819.49
Contractor's Profit 10% 0.1 181.95
Contractor's Overhead Expenses 3.5% 0.035 63.68
Total 2065.12
Add VAT with adjustment factor. 1.08108 7.5% 0.075 167.44
Grand Total 2232.56
Rate per sqm 223.3
Rate per sqm 223.3